United KingdomConstruction and engineering2024 – ongoing

Wates Group

Buildots construction monitoring and Delay Forecast

Wates used an AI warning to revise lighting work and reduce its forecast delay from 6 weeks to 1

WorkingVendor case studyVendor ↗

Problem

Wates project managers needed reliable progress information when discussing work with subcontractors. Disputes over progress made corrective action harder to agree.

Approach

Wates used Buildots to measure construction progress and flag delay risks. In March 2024, a lighting-installation warning prompted a manager to examine available work areas and installation pace. He agreed a revised strategy with the subcontractor, reducing the projected delay.

Results

1 weekprojected lighting-installation delay after intervention, down from 6 weeks, according to BuildotsVendor case study[1]

Takeaway

The warning led to a specific change in subcontractor planning. The reported improvement concerned the forecast schedule; Buildots did not report the final completion result.

Categories

Business function
Production and quality
Innovation type
Process innovation
Evidence
Vendor case study

Sources

Source summaries

[1]Buildots21 Aug 2024

Buildots described Wates using its progress measurements and delay forecasts in subcontractor discussions. Its lighting example reported a reduction in projected delay from 6 weeks to 1 after a revised work strategy.