National Highways
ALchera AI optimises M6 roadworks bookings
AI roadworks planning cut delayed journeys by 2,100 in a 2-month M6 trial
Problem
Roadworks schedules had to balance traffic disruption with safe working conditions.
Approach
Alchera used AI traffic predictions to select works bookings. Costain tested the system on the M6.
Results
2,100fewer delayed journeys during the two-month trial, as reported by Alchera
Takeaway
Consolidating work reduced disruption within the trial area.
Categories
- Size
- Large enterprise
- Industry
- Logistics and transport
- Business function
- Production and quality
- Innovation type
- Process innovation
- AI technology
- Predictive analytics and MLOptimization
- Adoption
- Vendor solution
- Evidence
- Vendor case study
Sources
Source summaries
[1]Construction Management2024
Construction Management reported the trial results. Estimated savings reached £45,000 through consolidated work.
Full details are in the original sources.
Added 1 Nov 2026 · Updated 1 Nov 2026