Conceição 2 'Model Plant' with AI process control (Itabira)

Vale said an AI-run iron ore plant in Itabira raised productivity 25% in under two years

WorkingCompany's own claimOfficial ↗

Problem

Vale's Conceição 2 iron ore processing plant in Itabira, Minas Gerais, had bottlenecks, and operators spent time in the field.

Approach

Vale rebuilt the plant over about 1.5 years with 51 solutions, with ABB as technology integrator. A data layer controls more than 400 variables, and AI layers adjust the process in real time using online ore-grade analysis. About 7,300 automated instruments and over 100 cameras support remote operation from control rooms. The plant was inaugurated on 10 June 2026.

Results

+25%plant productivity gain in under two years of the pilot, per ValeCompany's own claim[1][2]
-26%drop in average iron content in waste in 2026, per ValeCompany's own claim[1][2]
11.2 Mt/yrplant capacity reached, up from 9 Mt in 2024, per ValeCompany's own claim[1]

Takeaway

Vale combined AI process control with automated instruments and remote operation across the plant. The reported gains were the company's own figures.

Categories

Business function
Production and quality
Innovation type
Process innovation
Evidence
Company's own claim

Sources

Source summaries

[1]Vale10 Jun 2026

Vale reported a 25% productivity gain in under two years at its Conceição 2 plant, a 26% fall in iron content in waste, 11.2 Mt/yr capacity and 92% water recirculation. It lists the AI layers, 7,300 instruments and 51 solutions, and names ABB as integrator.

[2]InfoMoney10 Jun 2026

InfoMoney reported on the inauguration on 10 June 2026 and attributed the figures to Vale executives Carlos Medeiros and Rafael Bittar. It repeats the 25% productivity gain, the 26% fall in iron in tailings, the 51 solutions and the 1.5-year timeline.

Full details are in the original sources.